SCHEDULE AND BUDGET FOR COMPLETION OF HIGH SPEED SPECIAL PROCESSING UNIT

			     11 May 1973



Design of  the  Processor  is complete, including  logic
drawings, printed circuit  and wirewrap cards.  Assuming that certain
parts with a  total value of  $67,500 are  donated
by Digital Equipment Corporation  as expected,  the
project can be finished in about one year for the following cost.

			Personnel Costs

Salaries - 3 design engineers for 12 months,
	   plus 1 system programmer for 3 months  $50,000

Staff benefits (17%)				    8,500

Travel - 4 East coast @$500, 10 West coast @ $100   3,000

Miscellaneous direct costs			    3,000

Indirect costs (47% of above)			   30,315

	Personnel Subtotal				      94,815


			Parts and Services

Integrated circuits
	9000 TI and other		donated
	400 AMS memory chips		 31,000
						   31,000

Printed circuit cards
	Artwork for 24 cards @ $400	  9,600
	Fabricate 163 cards of 24 types  39,600
	Stuff & solder 110 @ $20,
	    25 @ $200			  7,200
						   56,400
Wirewrap cards
	Artwork				    600
	Card fabrication 65 @ $100	  6,500
	Sockets, capacitors 55 @ $135	  7,425
	Stuff and solder 55 @ 92	  5,060
	Wiring 55 @ $146		  8,030
						   27,615
Backpanel
	2 KI-10 bays with sockets	donated
	10,000 single wires @ .10	donated
	26,000 twisted pair @ .25	donated
							0
Power supplies
	cabinet				    800
	500 Amperes @ $10 per Amp.	  5,000
						    5,800

Cooling equipment				    1,000

Card tester					    3,000

	Parts and services subtotal			      124,815

	Project total					      219,630


				SCHEDULE

Week
1	Order ICs (from DEC and AMS), backpanel (DEC), wirewrap cards
	(Vostron), PC artwork (TRW), power supplies (Lambda), card
	tester (SOTTA).

2-3	Inspect PC artwork, order PC cards (Vostron).

4-9	Assemble card tester, debug tester and test programs.  Begin
	writing console computer software.  Monitor fabrication processes.

10-16	Delivery of wirewrap and PC cards.
12-20	Delivery of ICs.
16	Delivery of backpanel and power supplies.

11-25	Wirewrap card wrapping, stuffing, and testing (1 card per day).

13-30	PC card stuffing, soldering, and testing (2 cards/day + 2 weeks).

28-31	Final assembly and preliminary debugging.

32-52	Processor debugging, bringing up new system.

	                      NOTES

1. Delivery times of integrated circuits, etc. are based on quotes received
in January.  These times may be different now.

2. When an informal approval is received, some long lead time items could
be ordered on the basis of the donated money.