SCHEDULE AND BUDGET FOR COMPLETION OF HIGH SPEED SPECIAL PROCESSING UNIT
11 May 1973
Design of the Processor is complete, including logic
drawings, printed circuit and wirewrap cards. Assuming that certain
parts with a total value of $67,500 are donated
by Digital Equipment Corporation as expected, the
project can be finished in about one year for the following cost.
Personnel Costs
Salaries - 3 design engineers for 12 months,
plus 1 system programmer for 3 months $50,000
Staff benefits (17%) 8,500
Travel - 4 East coast @$500, 10 West coast @ $100 3,000
Miscellaneous direct costs 3,000
Indirect costs (47% of above) 30,315
Personnel Subtotal 94,815
Parts and Services
Integrated circuits
9000 TI and other donated
400 AMS memory chips 31,000
31,000
Printed circuit cards
Artwork for 24 cards @ $400 9,600
Fabricate 163 cards of 24 types 39,600
Stuff & solder 110 @ $20,
25 @ $200 7,200
56,400
Wirewrap cards
Artwork 600
Card fabrication 65 @ $100 6,500
Sockets, capacitors 55 @ $135 7,425
Stuff and solder 55 @ 92 5,060
Wiring 55 @ $146 8,030
27,615
Backpanel
2 KI-10 bays with sockets donated
10,000 single wires @ .10 donated
26,000 twisted pair @ .25 donated
0
Power supplies
cabinet 800
500 Amperes @ $10 per Amp. 5,000
5,800
Cooling equipment 1,000
Card tester 3,000
Parts and services subtotal 124,815
Project total 219,630
SCHEDULE
Week
1 Order ICs (from DEC and AMS), backpanel (DEC), wirewrap cards
(Vostron), PC artwork (TRW), power supplies (Lambda), card
tester (SOTTA).
2-3 Inspect PC artwork, order PC cards (Vostron).
4-9 Assemble card tester, debug tester and test programs. Begin
writing console computer software. Monitor fabrication processes.
10-16 Delivery of wirewrap and PC cards.
12-20 Delivery of ICs.
16 Delivery of backpanel and power supplies.
11-25 Wirewrap card wrapping, stuffing, and testing (1 card per day).
13-30 PC card stuffing, soldering, and testing (2 cards/day + 2 weeks).
28-31 Final assembly and preliminary debugging.
32-52 Processor debugging, bringing up new system.
NOTES
1. Delivery times of integrated circuits, etc. are based on quotes received
in January. These times may be different now.
2. When an informal approval is received, some long lead time items could
be ordered on the basis of the donated money.